– Re-habilitation of the sedimentation Tank
– Re-habilitation of the existing storage tank
– Repairs of leakages along the pipelines and the construction of the filtration unit.
– Evaluation by Nyasoso Cultural and Development Association and OSRI.
2nd Stage:
• Construction of the 40m3 storage tank and connection to the main line
Evaluation and provisional handing over.
Training of technical team for the repairs and maintenance of the water scheme will be done during the execution of the project and later on in a workshop and the class room.
A quarterly monitoring programme will be put in place by OSRI and the techinical team to assure smooth running of the scheme during one year before final handing over to Nyasoso Cultural and Development Association(NCDA)